production control and scheduling.
production control and scheduling.
consider the assembly network of a product as shown below. the number by the side of each node represents processing time in minutes. the required production volume in 8 hours shift is 24 completed assemblies. design an assembly line using rank positional weight method and compute its balancing efficiency.