A production process at Kenneth Day Manufacturing is shown in
the following figure. The drilling operation occurs separately
from, and simultaneously with, the sawing and sanding operations. A
product needs to go through only one of the three assembly
operations (the operations are in parallel). a) Which operation is
the bottleneck? b) What is the bottleneck time? c) What is the
throughput time of the overall system? d) If the firm operates 8
hours per day, 20 days p