5-2 Earned Value Calculation
5-2 Earned Value Calculation
5-2 Earned Value Calculation
Project Schedule and Budget Data Provided:
Task | Duration (days) | Predecessor(s) | Budget |
A | 2 | — | $1,600 |
B | 5 | — | $4,000 |
C | 3 | A | $14,050 |
D | 4 | B | $5,800 |
E | 6 | B | $12,000 |
F|4|C,D| $5200
G|3|E|$3900
5-2 Earned Value Calculation
Status of the project at the end of day 6:
Task | % Complete | Actual Cost of Work Performed |
A | 100% | $1,800 |
B | 100% | $4,500 |
C | 90% | $13,500 |
D | 10% | $500 |
E | 0% | $0 |
F | 0% | $0 |
G | 0% | $0 |
1. Calculate the schedule variance for each task and the total project.
2. Calculate the cost variance for each task and the total project.
3. What is your assessment of the project at this time?